Bridge Deck Sealing & Epoxy Overlay Project

The City of Chesterfield has contracted with RV Wagner, Inc. to perform a bridge maintenance project on the following bridges: Eagle Bluff Court, Chesterfield Ridge Center Drive, Timberlake Manor Drive, Schoettler Road, and Chesterfield Parkway Pedestrian Bridge. Work will include concrete sealing of the bridge decks, approach slabs, sidewalks, and barrier walls. The Chesterfield Ridge Center Drive bridge deck will receive an epoxy polymer overlay.
STATUS UPDATES:
08-28-2023 - The Chesterfield Ridge Center Drive epoxy overlay is scheduled to be performed on September 5, 2023. Chesterfield Ridge Center Drive will be closed on that day between North Outer 40 Road and Chesterfield Ridge Drive. Therefore, access to the top deck of the Chesterfield Ridge Center parking garage from Chesterfield Ridge Center Drive will also be closed on September 5, 2023. The other access from Swingley Ridge Drive will remain open.
08-01-2023 - The Chesterfield Ridge Center Drive epoxy overlay has been delayed due to bridge deck surface temperatures consistently exceeding manufacturer’s recommendations. The project will be completed by the end of September as temperatures cool.
06-29-2023 - Bridge sealing work is complete on Eagle Bluff Court, Timberlake Manor Drive, Schoettler Road, Ladue Road and the Chesterfield Parkway Pedestrian Bridge. The epoxy overlay work on Chesterfield Ridge Center Drive is scheduled to be performed in July. An exact date is still to be determined.
06-06-2023 - The bridge preventative maintenance project is scheduled to begin during the week of June 12, 2023 and finish by early August 2023. Traffic at each bridge is expected to be impacted by up to four days. The bridges on Eagle Bluff Court, Chesterfield Ridge Center Drive, Timberlake Manor Drive, and Schoettler Road will have single lane closures, but flaggers will be stationed to allow for traffic to pass in alternating directions during working hours. The deck sealing on the Ladue Road Bridge will require a lane closure and detour for eastbound traffic on Ladue Road, just east of Cross Trails Drive on two separate days. The exact dates for these closures are not yet known, but signage and detour routes will be posted prior to and during the closures. The Chesterfield Parkway Pedestrian Bridge will be closed to pedestrians for approximately four hours on two separate days.
05-01-2023 - City Council approved project bid from RV Wagner, Inc.
04-18-2023 - Project bids received and opened.