2024 Selective Slab Replacement Project-Area B

The City of Chesterfield plans to perform a slab replacement project on the following streets:

Clayton Douglas Court
Conway Springs Drive
Hitchcock Drive
Picket Court
Saylesville Court
Saylesville Drive
Signal Knob Court
Strawbridge Drive (Markham to Stablestone)
White Road (eyebrow only)

All work will be contained within the City’s Right-of-Way.  The work will include complete removal of the existing pavement and the placement of new pavement on the above-mentioned streets.  All sidewalk handicap ramps that intersect with this project will also be replaced to meet all ADA requirements.

Two-way traffic will be maintained throughout the project, though some minor delays can be expected.  Construction areas can be dangerous for workers and drivers alike. Please use caution while in the work zone for everyone’s safety.

 If you have any questions about the project, please contact Trent Helland at Thelland@Chesterfield.mo.us or 636-537-4758.

 PROJECT UPDATES 

5/14/2024 - Work on initial project 90% complete. Additional replacement work was also approved. This additional work is tentatively scheduled to start in late August and will include slab replacement on Bluffview Ridge Drive, Bluffview Ridge Court, and Bluffview Ridge Place.  
3/25/2024 - Start date. Phase one will begin on Georgetown Rd and Schoettler Manor Ct.
2/20/2024
- City Council Approval
2/6/2024 - Bid Opening