2024 Sidewalk Replacement Project A

The City of Chesterfield plans to perform sidewalk replacement within the following subdivisions:

Bent Tree
Chesterfield Meadows
Wilson Manor

The work will include removal and replacement of defective sidewalk sections, backfilling and seeding the newly constructed sidewalk sections.

Traffic will be maintained throughout the project, though some minor delays can be expected. Construction areas can be dangerous for workers and drivers alike. Please use caution while in the work zone for everyone’s safety.

If you have any questions about the project, please contact Matt Dooley at mdooley@chesterfield.mo.us or at 636-537-4766.


Project Updates

03-30-2024 - Construction completed. Contractor is currently addressing punch list items and submitting final paperwork.
03-11-2024
- Construction began.
02-20-2024
- City Council Approval

02-06-2024 - Bid Opening