The City of Chesterfield has been awarded a federal grant to construct a 5’ wide sidewalk on the east side of Schoettler Road, between Windsor Valley Court and Greenleaf Valley Drive. An existing retaining wall will also be relocated to the east to make room for the new sidewalk and improve vehicle site distance at that curve. Once complete, the project will fill the last remaining sidewalk gap on Schoettler Road and provide a pedestrian route on at least one side of Schoettler Road from Clayton Road to Chesterfield Parkway, and it will improve pedestrian access to the new Logan Park. The federal grant funding schedule specifies that engineering design will take place in 2024, right-of-way acquisition in 2025, and project construction in 2026.

 

STATUS UPDATES

 

10/2/2023  Negotiations began for Engineering design services with the engineering design firm deemed to be the most qualified. 

9/21/2023  RFQ Submittal deadline. Review began on the submittal packages from interested engineering design firms
.

8/23/2023  Request for Qualifications (RFQ) was posted to the MoDOT website to request Letters of Interest from qualified civil engineering design firms who would like to be considered for the project design.

 

8/14/2023  Program Agreement executed between the City and Missouri Department of Transportation (MoDOT).

 

6/8/2023  Grant formally awarded.

 

8/19/2022  Grant application submitted.