Schoettler Road

Schoettler Road Improvement Project

The City of Chesterfield plans to perform a construction project on Schoettler Road.  The limits of the work will be from Clayton Road to Georgetown Road/Schoettler Manor Court.  The project includes the addition of a center turn lane from Georgetown Road to Schoettler Grove Court and a designated right turn lane near Clayton Road.  The project also includes sidewalk along the east side of Schoettler Road from Amberleigh Hill Court to Schoettler Manor Court. Schoettler Road Project LimitsThe City contracted with HR Green, Inc. for design services associated with the project.  

The City has entered into a contract with Gershenson Construction Company, Inc., for construction of the project.

In order to safely and efficiently construct the project, Schoettler Road will be restricted to one-way southbound traffic from Georgetown Road/Schoettler Manor Court to Clayton Road during a portion of the construction.  A signed detour will be established for traffic wishing to travel north on Schoettler at Clayton Road.  The detour will route vehicles from Clayton Road to Baxter Road, to Old Baxter Road, to Highcroft Drive, and back to Schoettler Road.  It is anticipated that the one-way restriction will be in place for six to eight weeks.  

If you have any questions regarding Schoettler Road, please contact Jeff Paskiewicz, Senior Civil Engineer at jpaskiewicz@chesterfield.mo.us or by phone at 636-537-4759. 

To view the full set of construction plans, click on the image below.

Schoettler Road Construction Plans
                                                                   
          Project
 Detour Map
          Click on the image below to enlarge it



Project Updates:

2020-07-10:  The one-way restriction is scheduled to be removed on July 15, 2020 and two-way traffic will be restored on Schoettler Road.  Motorists will once again be able to travel northbound on Schoettler Road from Clayton Road.  Temporary striping will be placed on the new pavement such that two-way traffic can utilize the new pavement while the improvements to the west side of Schoettler Road are completed. 

2020-06-16:   The one-way restriction originally anticipated to be in place until late June will be extended until early July.  During excavation for the new pavement on the east side of Schoettler Road, unsuitable subgrade was encountered.  Removal of the unsuitable material and replacement with rock base was required.  This additional work will necessitate a delay in lifting the one-way restriction. 

2020-06-01:  
Gershenson Construction continued pouring concrete base widening and undercutting unsuitable soil in ditch line north of Amberleigh Hill Ct.

2020-05-26:    Gershenson Construction began pouring concrete base widening at Clayton Road and working their way north.

2020-05-14:    Missouri American Water Company transferred service over to the relocated main.  As part of the transfer a 4 hour service interruption was necessary.

2020-05-13:  Gershenson Construction working on removals and began setting forms for concrete base widening. 

2020-05-12:  
Parkway School District and Spectrum completed relocation of their communications lines and Ameren removed the old poles.

2020-05-06:  Missouri American Water Company begin relocation of the water main south of Georgetown Road.

2020-04-29:  The one-way southbound lane restriction was put in place and work began on the project.

2020-04-22: Changeable message boards were placed on Clayton Road and Henry Avenue.  Message on the boards provides advance notice of the south bound restriction beginning on April 29, 2020. 

2020-04-20: Preconstruction meeting held.  Work on the project is scheduled to begin on April 29, 2020.  The one-way south bound restriction will begin on April 29, 2020.
 
2020-3-23:
  AT&T and Ameren are currently working on relocations to facilitate construction of the project. 

2020-03-16:  City Council authorized staff to enter into an agreement with Gershenson Construction Company Inc. for construction of the project.

2020-03-04:  Public meeting held at City Hall.

2020-03-03: Bid opening held.

2020-02-20:  A public meeting is scheduled for March 4, 2020 from 4:00 PM to 7:00 PM at Chesterfield City Hall.  The purpose of the meeting is to provide information to residents regarding the one-way south bound restriction and answer any questions.

2020-02-18: Project was advertised for bid.  A pre-bid meeting will be held on February 25, 2020 and bids will be opened on March 3, 2020.