Old Chesterfield Road Culvert Replacement Project

Old Chesterfield Road Culvert Replacement Project

The City of Chesterfield has a stormwater and roadway improvement project planned for Old Chesterfield Road.  The project includes replacement of the culvert located east of the Breckenridge Ready Mix Plant and resurfacing of the asphalt portion of Old Chesterfield Road.


The City contracted with Oates and Associates for design services associated with the project.  Construction is scheduled to begin in early Summer 2020 and will be completed by early fall 2020.

In order to replace the culvert, it will be necessary to close Old Chesterfield Road between the entrance to the Chesterfield Mobile Home Park and Ameren’s power substation located at 16618 Old Chesterfield Road.  Access to all properties located on Old Chesterfield Road will be maintained.  A signed detour route will be established to direct traffic around the closure via Baxter and Wild Horse Creek Road.  The closure is currently scheduled to begin in late May of 2020 and will be in place until late August 2020.  The exact timing of the closure will not be finalized until a contractor has been selected and a detailed schedule provided and approved by the City.

If you have any questions regarding Old Chesterfield Road, please contact Jeff Paskiewicz, Senior Civil Engineer at jpaskiewicz@chesterfield.mo.us or by phone at 636-537-4759.

To view the full set of construction plans, click on the image below.

Old Chesterfield Road Culvert Project

Project Updates:

2020-03-24:  Bid documents made available for bidding purposes with bid opening scheduled for 4/7/20 at 11:00 a.m. at City Hall.

2020-03-04:  Public meeting held at City Hall.

2020-02-20:  A public meeting is scheduled for March 4, 2020 from 4:00 p.m. to 7:00 p.m. at Chesterfield City Hall.  The purpose of the meeting is to provide information to residents regarding the road closure and answer any questions.