2023 Sidewalk Leveling Project Area A
This project will level sidewalk sections to remove deficiencies through the use of a mud-jacking process. Sidewalk leveling is planned within Chesterfield Meadows, Wilson Manor, Bent Tree and a portion of Wilson Farm. The Sidewalk Leveling Project allows the City to repair additional sidewalk by reducing the number of slabs that require full removal and replacement within the Sidewalk A Project.
Construction is scheduled to begin the week of April 17, 2023 substantial completion is expected approximately June 16, 2023 weather dependent.
Traffic will be maintained throughout the project, though some minor delays can be expected. Construction areas can be dangerous for workers and drivers alike. Please use caution while in the work zone for everyone’s safety.
If you have any questions about the project, please contact Matt Dooley at mdooley@chesterfield.mo.us or at 636-537-4766.
Project Updates
05-04-2023 - Project complete
04-17-2023 - Project began in the Wilson Farm Subdivision
02-21-2023 - City Council Approval
02-07-2023 - Bid opening