2023 Selective Slab Replacement Project-Area B

The City of Chesterfield plans to perform a slab replacement project on the following streets:

Royalbrook Drive
Whitestone Farm Drive
Country Field Court


All work will be contained within the City’s Right-of-Way.  The work will include complete removal of the existing pavement and the placement of new pavement on the above-mentioned streets.  All sidewalk handicap ramps that intersect with this project will also be replaced to meet all ADA requirements.

Construction is scheduled to begin in March and substantial completion is expected approximately in October, weather dependent.

Emergency services, the United States Postal Service, trash services, and the school district have all been notified of the project and services will not be impacted.

Two-way traffic will be maintained throughout the project, though some minor delays can be expected.  Construction areas can be dangerous for workers and drivers alike.  Please use caution while in the work zone for everyone’s safety.

 If you have any questions about the project, please contact Trent Helland at Thelland@Chesterfield.mo.us or 636-537-4758.

 PROJECT UPDATES

08-16-2023 - Project closed.
08-10-2023 
- Project completed.
05-15-2023
- Week of 5/15 - Phase Five on Royalbrook Drive started on 5/15.  Phase Three on Whitestone Darm Drive opened to traffic.  Phase Four on Whitestone Farm Drive scheduled to start on 5/18.
05-08-2023
- Week of 5/8 -Phase Two opened and Phase Three started on Whitestone Farm Drive.  Phase Two on Royalbrook Drive will be opened on 5/9.  Phase Three on Royalbrook Drive is scheduled to start on 5/10 but is dependent on weather.
05-01-2023 
- Week of 5/1 - Phase Two on royalbrook Drive will be opened and Phage Three is tentatively scheduled to start on 5/3.  This will include a section of Phase One (14913 to 14921) to be redone and one-half of the intersection with Baxter Road.  Phase Two on Whitestone Drive was started on 5/1.  
04-24-2023
 - Week of 4/24 - Phase One opened and Phase Two on Royalbrook Drive has been started. Phase One on Whitestone Fam Drive is scheduled to be opened on 4/26 and removal of Phase Two to start.
04-17-2023 - Phase one on Royalbrook Drive and Whitestone Farm Drive is scheduled to be completed the week of 04/17/2023. 
04-10-2023 – Construction starting on Royalbrook Drive and Whitestone Farm Drive the week of 04/10/2023.